March – May 2026 – Completion of flooring and ceiling cladding Following the Ramadan period, our developer has resumed construction work on the health centre. The following work has been completed: Plastering of the external walls Installation of ceiling panelling and...
by Christine Masuch | Juneth June 2025 | Midwife counselling station 2, Project
27.01.2025 – 03.05.2025 Completion of the exterior and interior walls The construction workers completed the exterior and interior walls as well as the entrance area of the building in just over a month. To ensure that the building is stable, iron girders were...