27.01.2025 – 03.05.2025 Completion of the exterior and interior walls

The construction workers completed the exterior and interior walls as well as the entrance area of the building in just over a month.

To ensure that the building is stable, iron girders were embedded in all the walls above and below the windows. This is also the reason why all the interior walls were completed.

Due to the resulting increase in construction costs, our funds were no longer sufficient for the roof and windows. So from March onwards, construction was at a standstill, well timed with Ramadan. During Ramadan in March, construction would have had to pause even with money.

 

Bau des Eingangsbereichs

15.05.- 19.06.2025 Roofing and installation of windows and doors

Due to several large donations, we have been able to raise a lot more money since January, so that we were able to transfer another € 6,000 to Burkina Faso in the week of 12 May – 18 May 2025. This was used to buy the windows and doors and cover the roof. On 19 June 2025, the building was completed apart from a few minor details.